Many perspective new home buyers are watching
Extreme Home Makeover and believe
that a new home can be constructed in a short period of time. WRONG. There is TV
Reality
and then the real world.
Constructing a new home can take anywhere from six months to one year (or more),
depending on a number of factors. The size of the house, number of workers,
weather conditions, and unexpected--but inevitable--delays all make a
difference. Though the order of work may vary slightly and local
building-inspection requirements differ, this timetable, spread over a
seven-month period, should give you a pretty good sense of what to expect and
when:
Months 1 & 2
- Obtain municipal and state permits
- Begin site work and excavation
- Homesite scraped, leveled and pinned.
- Erosion controls in place.

- Slab form boards set.
- Underground plumbing in place.
- Type II and vapor barrier in place.
-
Pre-slab pour inspection completed.
- Slab poured.
- In some locations, flat work (sidewalks, patios and driveways) is
formed, and the concrete is poured.
- Slab form boards pulled.
- Rough grade completed.
- Frame floors
- Rough-in electrical and plumbing under
floors
- Install first-floor subfloor
Months 2 & 3
- Frame walls, roof and ceilings, including
all door and window rough openings

- Exterior sheathing installed.
- Windows installed.
- Roof sheathing completed.
- Roof nailing completed.
- Roof tiles or shingle material loaded.
- Install remaining subfloors
- Apply exterior wall and roof sheathing
- Rough-in remaining electrical and plumbing
lines in wall, ceiling and floor cavities
- Rough plumbing installed.
- Rough HVAC (Heating, Ventilation, and Air-Conditioning) installed.
- Rough electrical installed.
-
-
Months 3 & 4
- Rough frame inspections (municipal inspections: mechanical, plumbing,
electrical and frame) completed.
- Apply roof flashing and shingles
- Install windows and exterior doors

- Batts installed (wall insulation).
- Drywall stacked or scheduled.
-
Pre-drywall Inspections
- Drywall installed throughout the home.
- Drywall nailing inspection completed.
- Ceiling insulation installed (per plan). Note: not required between 1st
and 2nd floors.
- Drywall taped and textured in accordance with the approved home plan.
- Exterior finishes will be started (brick, cementatious finish, stone or
siding).
- Apply exterior trim
Months 5 & 6
-
- Apply ceramic tile in baths
- Finish plumbing and electrical work
- Paint and wallpaper
- Install finish flooring
- Garage doors installed.
- Interior door casings and doors installed.

- All cabinets installed.
- Base molding installation complete.
- Ceiling molding and chair molding installed (if required per the
approved plan).
- Staircase railing and balusters installed (two story homes).
Months 6 & 7
- Finish electrical installed and operationally tested.
- Finish plumbing installed and operationally tested.
- Finish HVAC installed and operationally tested.
- All flooring installed.
- Appliances installed.
- In some locations, flat work (sidewalks, patios and driveways) is
formed, and the concrete is poured.
- Interior painting applied.
- All countertops installed.
- Mirrors and shower enclosures installed.
- Outside landscaping is started (weather permitting).
- Install final hardware
-
Final Inspection
- Touch-up for final inspection by homeowner
- Owner final walk-through
- Move in
Most builder truly intend to build a near perfect home.
The only way you can be assured of this is by
having an independent
inspection. This is our business and we are very good at ferreting out
issues that could have a dramatic and expensive impact on your home
ownership. Please give us a call @ 360-588-6956 to book an inspection.
TIMING FACTORS
There
are several variables that can affect the completion of your new home. We have
outlined some of these variables below to help you better understand how the
construction of your new home can be affected.
Weather
One of the most obvious
factors that can affect construction schedules is the weather. Depending on the
severity of weather conditions your project can virtually stall - standing
water, mud and extreme cold can take its toll. That's why most builders will
want to start projects in spring and have the home weather tight prior to fall.
While your construction site might not experience severe weather directly, weather in
other parts of the country can also affect the construction time of your home. Manufacturing facilities in various locations can be adversely affected by
weather, requiring temporary shutdowns or disruption of shipping. Interruptions
like these can lead to a backlog of orders for manufacturers, which in turn, can
create delays in receiving materials.
Permit and Inspection Process
During the construction process, your builder will work with various governmental organizations to
secure permits prior to the construction of your new home. As your home
moves through the stages of construction, there will be several required
inspections. Inspections are generally carried out by the municipality or
county. These inspection only ensure that your home meets the minimum standards
set by the city or county. Most new home buyers don't understand this and forego
an independent inspection. Want to see what these inspector miss?
Look at our hall of shame
Labor and Materials
However, there are times
when situations beyond your builders control can affect labor or materials.
As you know,
there are many different materials that go into constructing your new home. As
the construction of your home proceeds, the materials for the next stage of
construction are delivered. Because our manufacturers continuously review
and improve their product lines, there are times when items that were available
when your home was started are discontinued. These unanticipated changes can
affect construction schedules. In some cases, the popularity of an item can also lead to
material shortages and back orders.
In addition, the labor force in various areas of the country can be impacted by
natural disasters, such as when numerous homes sustain damage from hurricanes or
earthquakes, stretching the labor force thin across all construction-related
industries. Labor strikes can also have a major impact on the construction
process.
|
Powered by counter.bloke.com
|
Pacific Crest Inspections Home Inspections
5116 Heather Dr, Anacortes, Washington 98221
Toll Free
1-866-618-7764 or 360-588-9956

|
Pacific Crest Inspections is a locally owned and certified home
inspection company providing home inspections, commercial inspection and pest
inspections in the Mt. Vernon, Wa. area. Pacific Crest inspections is licensed
by Washington State and carries the highest certification “Certified Real Estate
Inspection” offered by the National Association of Home Inspectors (NAHI)
Pacific Crest Inspections conducts their Washington State home inspections
according to the National Association of Home Inspectors
Standards of Practice & Code of Ethics. These
professional home inspection standards provide a minimum guideline for
conducting a Mt. Vernon, Washington home inspection. Our home inspection
standards are available for viewing under the "Consumer Information" section of
our website or ask your Washington home inspector for a copy of the NAHI Standards
of Practice & Code of Ethics prior to your Mt. Vernon home inspection.